VALUE: £2.1m CLIENT: SPIRIT ENERGY PROJECT: MORECAMBE BAY TERMINAL, BARROW   South Morecambe Field covers an area of 32 square miles of Morecambe Bay with a total of 35 wells and an accommodation platform for this field. The Gas was transferred by undersea pipeline to the South Morecambe Terminal....

VALUE: £24m+ CLIENT: Redacted for confidentiality purposes PROJECT: AROMATICS PLANT 1 & 2   The site is located within the North Tees site, which occupies a large plot on the north bank of the River Tees. The works comprise of the hazardous insulating material removal, dismantling, demolition and site...

VALUE: £5.2m CLIENT: INEOS PROJECT: GRANGEMOUTH OIL REFINERY   Thompsons were awarded the Contract in January 2017 to demolish a number of plot areas within the live INEOS refinery tier 1 COMAH site. The Plot Areas were; Plot 4 (Benzene) Plot 5 (Gas Treatment Unit) Plot 5a (Hydro Isomerisation...

VALUE: £310k CLIENT: NORTHERN GAS NETWORKS PROJECT: GAS HOLDER, JARROW   Thompsons were appointed by Northern Gas Networks (NGN) to undertake the demolition of the Jarrow Gas Holder, located on Curlew Road in Jarrow, Tyne & Wear.  The site was located within proximity to several sensitive stakeholders and with...

VALUE: £3.1m CLIENT: BLUESTAR FIBRES PROJECT: BLUESTAR FIBRES Ph2-5, GRIMSBY   Following extensive pre-qualifying considerations, Thompsons were contracted as Principal Contractor by Bluestar Fibres, Moody Lane, Grimsby for the first time to carry out the subsequent phases of Bluestar’s site rationalization Programme to prepare and remove the plant which...